LIVE
NIVESH STREET_
LIVE MARKET INTELLIGENCE
NIFTY 50 25,181.80 +1.38%SENSEX 72,472.33 +1.23%BANK NIFTY 55,256.65 +1.36%INDIA VIX 14.38 -0.42%GOLD ₹1,21,540 +0.61%BTC/USD $112,480 +2.14%USD/INR 88.42 -0.08%CRUDE $84.16 +0.94%NIFTY 50 25,181.80 +1.38%SENSEX 72,472.33 +1.23%BANK NIFTY 55,256.65 +1.36%INDIA VIX 14.38 -0.42%GOLD ₹1,21,540 +0.61%BTC/USD $112,480 +2.14%USD/INR 88.42 -0.08%CRUDE $84.16 +0.94%
Live
NIFTY 5022,811.35▼ 0.34%
SENSEX73,709.69▼ 0.19%
BANK NIFTY54,976.9▼ 0.92%
NIFTY IT32,422.5▲ 2.88%
NIFTY MIDCAP16,500.2▼ 1.60%
INDIA VIX15.68▲ 6.16%
Gold (24K)4,043.4▼ 2.57%
Silver54.71▼ 4.73%
Copper6.41▼ 2.09%
Crude Oil (Brent)113.22▲ 4.04%
Natural Gas2.78▼ 0.29%
USD/INR94.81▲ 0.10%
Bitcoin81,313.9▼ 3.21%
Ethereum2,383.3▼ 3.54%
Solana103.36▼ 3.22%
BNB731.02▼ 1.99%
XRP1.3▼ 4.53%
Cardano0.21▼ 5.91%
Dogecoin0.08▲ 4.06%
NIFTY 5022,811.35▼ 0.34%
SENSEX73,709.69▼ 0.19%
BANK NIFTY54,976.9▼ 0.92%
NIFTY IT32,422.5▲ 2.88%
NIFTY MIDCAP16,500.2▼ 1.60%
INDIA VIX15.68▲ 6.16%
Gold (24K)4,043.4▼ 2.57%
Silver54.71▼ 4.73%
Copper6.41▼ 2.09%
Crude Oil (Brent)113.22▲ 4.04%
Natural Gas2.78▼ 0.29%
USD/INR94.81▲ 0.10%
Bitcoin81,313.9▼ 3.21%
Ethereum2,383.3▼ 3.54%
Solana103.36▼ 3.22%
BNB731.02▼ 1.99%
XRP1.3▼ 4.53%
Cardano0.21▼ 5.91%
Dogecoin0.08▲ 4.06%
ECONOMY 51m ago

Centre flags land, green tape hurdles in infra projects

Economic Times Economy
Published 22 Oct 2026, 07:21 pm IST

Listen to this article in summarized format

A man works on a construction site of a residential building in Mumbai, India, October 31, 2016.Reuters

The key trigger: While the national $30-trillion economy ambition rests considerably on central sector linear infrastructure projects, a PRAGATI-based project analysis reveals that 75% of delays are due to four 'pre-construction' factors: land acquisition/right of way, green clearances, utility shifting and state permissions.

Points shared with states:

* Cost for central linear projects jumped up by ₹3 lakh crore over original cost of ₹31 lakh crore due to pre-construction linked delays.

You Might Also Like thumb-134798765

Experiments on animals set to become easier

* A PRAGATI review of over 3,300 infrastructure projects worth ₹85 lakh crore revealed that delays due to land acquisition accounted for the highest -- 35% of all issues.

* Forest clearances, which should be granted within 150 days, are taking over 500 days. Wildlife clearance processes stretch 1.5-3.5 years while environmental clearances can take 180 days to 2.5 years.

* Average time for completing utility shifting is 500-600 days against the expected 200-300 days.

* Developers of central linear infrastructure are required to obtain 22 approvals/permits across 16 different state agencies in the absence of single window mechanisms.

You Might Also Like thumb-135000743

Amid Special Intesive Revision, about 20 Chief Election Officers transferred in 20 Months

Land acquisition is the top delay-causing factor. A 'land acquisition efficiency' ranking of states conducted by the Ministry of Road Transport & Highways (MORTH) shows that Haryana tops the rankings with a 75.8 score followed by Madhya Pradesh (66.2), Rajasthan (65.9), Andhra Pradesh (63.8) and Chhattisgarh and Kerala at 63. Surprisingly, Tamil Nadu (45.4), Maharashtra (43.6) and Gujarat at the bottom with 30.5 score earned on efficiency of land acquisition for national highways.

Environment ministry's PARIVESH 2.0 analysis shows that time taken for forest, wildlife and environmental clearances cumulatively, including state and central agencies, ranges 2-4 years. Despite the Union Environment ministry undertaking multiple reforms to reduce time at their end from 105 days to 61 days for environmental clearance, linear projects continue to face 'long delays in getting approvals'.

Utility shifting involving water, sewer pipes, electricity cables and towers continues to be a pain point -- the average time for utility shifting is 500-600 days against the expected 200-300 days. Add to this the numerous state-administered permissions for project sites, construction material and equipment.

SOLUTIONS PROPOSED

*A single, time-bound, portal-based process for land acquisition and green clearances processed parallelly, rather than sequentially

* Utility shifting to be treated as a project in itself with clear timelines and accountability

* A single point of ownership in every state for construction-input permission and pre-construction readiness.

Originally reported by Economic Times Economy.Source: economictimes.indiatimes.com